SEM-26-009

Margarita Maza Dam Project

September 22, 2026 Mexico

Proyecto de Presa Margarita Maza
i
Latest Update - September 22, 2026

The Secretariat began reviewing the submission under Articles 24.27(2) and (3) of the USMCA.

Status: Open

Summary of the matter addressed in the submission:

The Submitter asserts that Mexico is failing to effectively enforce its environmental laws with respect to the assessment of the environmental impacts of the Margarita Maza dam, also known as the Mujer Solteca dam. The dam is intended to supply drinking water to the State of Oaxaca in Mexico.

According to the submission, the construction of the dam began on 10 June 2026, before the regional environmental impact statement (manifestación de impacto ambiental, MIA) was approved. In particular, the Submitter claims that the Ministry of the Environment and Natural Resources (Secretaría de Medio Ambiente y Recursos Naturales, Semarnat) did not respond to their request for a public consultation of the project and did not follow the procedures and timelines for public participation established in applicable environmental laws.

Names and citations of the environmental laws in question:

Submitter(s):

Name withheld pursuant to Article 16(1)(a) of the ECA

Submission Timeline

1 / 10 steps completed

Submission Timeline

September 22, 2026

The Secretariat began reviewing the submission under Articles 24.27(2) and (3) of the USMCA.

Submission - Submission authored by Submitter(s) on 22/09/2026

Annex - Other document authored by Submitter(s) on 22/09/2026

Annex - Other document authored by Submitter(s) on 22/09/2026

Annex - Other document authored by Submitter(s) on 22/09/2026

Annex - Other document authored by Submitter(s) on 22/09/2026

Annex - Other document authored by Submitter(s) on 22/09/2026

Annex - Other document authored by Submitter(s) on 22/09/2026

Annex - Other document authored by Submitter(s) on 22/09/2026

Annex - Other document authored by Submitter(s) on 22/09/2026

Annex - Other document authored by Submitter(s) on 22/09/2026

Acknowledgement - Communication to Submitter(s) authored by Submitter(s) on 23/09/2026